CDPR
>
Vietnam
After 20 months of operations (out of 48), the
CDPR has achieved the following (intermediary) results:
1. The first
Law on Public Investment of Vietnam was prepared with the support of the
CDPR. The Public Investment Law (PIL) became effective in January 2015. The
CDPR supported many consultation workshops for the finalization of the law as
well as training for its implementation. The Law creates a completely new legal
framework for the management of the entire public investment process, from
investment decision, capital source verification to project implementation,
monitoring and evaluation. The 2015 Law on Public Investment is referred to as a
revolution in the management of public investment in Vietnam.
2. The project provided support to the
preparation of the decree 77/2015/ND-CP providing instructions for the Medium Term Investment Plan (MTIP).This
provided the framework for managing public investment in a multiyear perspective
rather than through annual budget.
3. The project provided support to the Ministry
of Planning and Investment (MPI) in the formulation of a decree providing
instruction on the implementation of the
Law on Public Investment.
4. The CDPR supported MPI in drafting a directive
for the preparation of the
Socio-Economic Development Plan (SEDP) 2016-2020 and for MTIP for 2016-2020
5. The project organized training
workshops for the 64 provinces of Vietnam in the preparation of the MTIP
2016-2020.
6. The project also supported the preparation of Decision no.
40/2015/QD-TTg defining the principles and criterias for allocating State capital budget for the 2016-2020 period. This is a
crucial document which defied the way capital budget will be allocated to
different provinces of Vietnam.
7. The project initiated the capacity assessment of the 64 provinces on PIL and MTIP implementation.
This was done through questionnaire sent to all the provinces of Vietnam. A capacity
assessment of the five pilot provinces of the project was initiated.
8. A website containing all information’s related to the PIL and MTIP for
local authorities and line ministries was also launched: http://www.cdpr.org.vn/index.php/vi/
The project overall expenditures as of
31/12/2015 amount to 1,312,185 EUR which gives an execution rate of 33 %.
Pas d'actualité